Two new MET solar parks have started production in Hungary

Mihai-Alexandru Cristea 27/01/2023 | 17:01

MET Group has completed the construction works of MET Gerjen Solar Park and MET Söjtör Solar Park, both in Hungary, and the solar power plants have commenced commercial operations. The investments cover an area of 170 hectares altogether in the two municipalities, where almost 180.000 solar panels have been installed, adding 96 MWp of green energy into the grid. The completion of the projects was celebrated with a ribbon-cutting ceremony.

 

The solar parks join the electricity grid through newly installed high-voltage substations. The commissioning of MET Gerjen Solar Park (51 MWp) and MET Söjtör Solar Park (45 MWp) took place over several phases. The two plants will generate enough green electricity to cover the consumption of around 50 thousand households.

To refinance two existing solar parks (MET Dunai Solar Park and MET Kabai Solar Park), as well as to finance the acquisition and construction of three new solar farms (among them the plants in Gerjen and Söjtör), MET Group subsidiary MET Hungary Solar Park Kft. successfully issued a bond in 2021 that subsequently achieved a green rating as well.

As improving local quality of life is also an important part of the implementation, MET Group carried out indoor and outdoor improvements to local kindergartens and schools.

MET’s renewables expansion strategy aims to reach a 2 GW installed capacity portfolio by 2026, thus playing an active role in the European energy transition. As part of this overarching strategy, MET Group and Singapore-based Keppel Infrastructure formed a JV company in November 2022, Keppel MET Renewables, to pursue renewable energy opportunities in Europe. Over the past year, MET Group was able to enter the renewables market in four new countries, with acquisitions in Spain, Italy, Poland, and Romania.

In Romania, MET Group has acquired a 100% stake in a solar project at an advanced stage of planning. The 52 MWp project could be ready-to-build by the first quarter of 2023. The park, can also reach an energy output of about 82 GWh per year – equivalent to the annual consumption of about 50 thousand households. Located in southern Romania, near Bucharest, the project is expected to become operational in 2024.

BR Magazine | Latest Issue

Download PDF: Business Review Magazine April 2024 Issue

The April 2024 issue of Business Review Magazine is now available in digital format, featuring the main cover story titled “Caring for People and for the Planet”. To download the magazine in
Mihai-Alexandru Cristea | 12/04/2024 | 17:28
Advertisement Advertisement
Close ×

We use cookies for keeping our website reliable and secure, personalising content and ads, providing social media features and to analyse how our website is used.

Accept & continue