![](https://media.business-review.eu/unsafe/420x250/smart/filters:contrast(5):quality(80)/business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0Sud_L3_ruta_ce_conecteaza_A0_cu_A1_iunie_2024.jpg)
The Greek builder AKTOR is keeping up the pace of work for the A0 L3 highway section in the south of Bucharest, being close to the threshold of 70% physical execution stage of the project.
You can watch recent footage here. The images in the article are illustrative.
The A0 South Lot 3 section has a length of 18 km, of which 15.465 km are part of the South Belt, and 2.5 km of the North Belt, separated by the A1 highway towards Pitesti. Of the total length of 18 km, AKTOR has already laid the first layer of AB2 asphalt on 10.5 km.
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0Sud_L3_lucrari_asfaltare_2-1024x576.jpeg)
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0Sud_L3_lucrari_asfaltare_1-768x1024.jpeg)
The route connecting A0 with A1 takes shape:
At the CFR bridge over the Bucharest – Craiova railway, pallets are installed. The last precast concrete beams will be installed in July.
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0Sud_L3_podul_CF_iunie_2024-1024x495.jpg)
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0SudL3_CF-P2-P3d-predale_iunie_2024-576x1024.jpeg)
Site mobilization is increased, despite the high temperatures during this period.
For example, at the DC 126 crossing over the highway at km 86+791 (Clinceni), the elevation is concreted.
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0SudL3_DC-126-P1-betonare-elevatie_iunie_2024-576x1024.jpeg)
At the DC 182 crossing over the highway at km 94+280, concreting works were carried out last week.
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0Sud_L3_DC-128-betonare-trotuar-dreapta_iunie_2024-576x1024.jpeg)
The constructor also progressed in other key points of the segment: the passage over DJ 601 at km 98+272 (Ciorogârla) or the bridge over the Ciorogârla river at km 99+932 (Ciorogârla).
![](https://business-review.eu/wp-content/uploads/2024/06/1.AKTOR_A0SudL3_DJ601-deschiderea-1-dreapta-cale-1_iunie_2024-1024x576.jpeg)
In addition to the crossing over the A1, in the Ciorogârla area, AKTOR is building on the A0 Sud Lot 3 segment another 4 bridges, 6 passages (overpasses), 46 footbridges, two temporary parking lots, and two service spaces. At the beginning of June, the 11 structures (bridges and overpasses) were 70% complete.
The project also includes earthworks, construction of embankments, fencing, barriers, parapets, horizontal and vertical markings and signalling elements, lighting system, highway communication systems, public recreation areas, landscaping and landscaping works the land.
AKTOR Construction is a member of the Intrakat Group, an industry leader in the Greek sectors of construction, infrastructure, concessions/public-private partnerships (PPP), renewable energy sources (RES), energy storage, real estate development, environmental projects and digital technologies, with a significant presence in Southeast Europe, listed on the Athens Stock Exchange since 2001.
***